Stearns County Ditch 28 (CD28) - Proposed Project 2020
If you have questions pertaining to the CD28 Proposed 2020 projects after reading the information below, please call 320-654-4703.
Stearns County has been actively reviewing the drainage system to react to complaints of flooding. The goal has been to understand the issues and condition of the ditch and then determine an appropriate action plan. This page is meant to be a resource for property owners to understand past, present, and future projects that may incur costs for the ditch system.
Any costs incurred by the drainage system are paid by property owners in the system through special assessments.
At the November 17 Board of Commissioners meeting, a project will be discussed regarding spending an estimated $25,000 to $30,000 that the property owners on the CD28 system will be responsible for paying for.
The CD28 Property Owner Presenation is a great place to start if you have a lot of questions about the projects being discussed.
CD28 Property Owner Presenation - Video
CD28 Property Owner Presenation - Slides
The following project is being considered for approval at a future Stearns County Board of Commissioners meeting.
At an estimated cost of $25,000 to $30,000, a Engineer’s Repair Report has been recommended by the engineering experts hired by Stearns County to evaluate the system. The Repair Report would detail the necessary repairs to CD28, the estimated cost of repairs, and detailed plans and specifications necessary to prepare and award a contract for repairs.
If the Repair Report is approved by the five County Commissioners acting as the Drainage Authority for CD28, an engineer will be hired to complete the Repair Report.
It is important to note that approval of the Repair Report could lead to a Ditch Redetermination Project and a Repair to CD28. Click the link below for more information about the cost and details of those projects.
Repair Project and Cost Summary
The Estimated Cost per Acre document linked below, represents a crude estimation of how costs might look for property owners in a redeterminated drainage system. It should be noted that these values represent an equal distribution of dollars across properties and we know that is not how Ditch Viewers would calculate property owners share of the project. The spreadsheet is for planning purposes only and individual property bills WILL change if a Ditch Redetermination project is ordered by the Stearns County Commissioners.
11/17/2020
At the County Board of Commissioners meeting held November 17, 2020, staff presented a summary report of all the feedback received as of Oct. 23, 2020 regarding potential projects on CD28. The Commissioners, acting as the drainage authority for CD28 passed a unanimous motion to accept the public feedback report and based on property owner feedback, engineers inspection report, and estimated costs, directs staff to monitor and inspect the impact of the removal of the fish trap in 2021 and present an updated inspection report to the drainage authority. The motion also approved tax assessment for 2021 in the amount of $20,067.94 to pay for projects performed in 2020.
You can view the summary report of the feedback from the public survey using the link below.
Please click the link below for details of special property tax assessment in the amount of $20,067.94:
Board of Commissioners Meeting Minutes
11/13/2020
Below is information regarding CD28 information that will be presented to the Board of Commissioners on November 17, 2020 scheduled for 9:40am. The presentation of the feedback received from the recent CD28 project survey will be presented to the Stearns County Commissioners. You can view the summary report of the feedback from the public survey using the link below.
The link below contains the meeting agenda and once the Commissioners meeting has started, this same page will contain a link to open the video of the meeting.
http://stearnscountymn.iqm2.com/Citizens/Default.aspx
11/2/2020
November 17, 2020 Board of Commissioners Update
On Nov. 17, 2020, staff will be presenting the feedback received by letter, phone, and surveys regarding the potential for projects on the CD28 drainage system. The meeting will be virtual and people cannot attend in person unless there is a change in county policy before the meeting. The public is invited to watch online. For meeting agendas and to watch, click the link below. There will be a link to watch the meeting at 9:00am the day of the meeting.
http://stearnscountymn.iqm2.com/Citizens/Default.aspx
Ditch Frequently Asked Questions
Engineer’s Re-establishment of Records
Based on the recent engineer report performed on CD28 from lake outlet to ditch end at the Co Rd 17 culverts, mapping was developed to help demonstrate where water is predicted to go based on certain scenarios. The engineering vendor hired by Stearns County takes all the data available and uses a computer model to produce the findings. Using the GIS interactive map found at the link below, you can turn on and off different map layers and scenarios to zoom in and see the computer modeled results. The disclaimer on this data is that it is a predictive model and not based on actual events.